Glenwood Drive Bridge Replacement Over Tinkers Creek

Share Glenwood Drive Bridge Replacement Over Tinkers Creek on Facebook Share Glenwood Drive Bridge Replacement Over Tinkers Creek on Twitter Share Glenwood Drive Bridge Replacement Over Tinkers Creek on Linkedin Email Glenwood Drive Bridge Replacement Over Tinkers Creek link

The City of Twinsburg had been in discussions with Summit County Engineers office for a number of years about replacing the Glenwood Drive bridge over Tinkers Creek. In 2022 the bridge inspection indicated that the structure needed to be posted with load restrictions and was posted with load restriction warning signs. This moved the project up in priority and helped in securing funding for this project. The table below indicates estimated cost in 2023 dollars that will be adjusted for inflation per the funding guidelines based on the actual year of construction. The County is the owner of the bridge and the lead on this project with construction anticipated in 2028.

The City participation in the project is for sidewalks and aesthetics to be included in the design. Also included with the bridge project will be a waterline replacement of a line that is currently attached to the underside of the bridge. The waterline is to be funded 100% funded by the City of Twinsburg and we anticipate submitting an OPWC application in 2026 for additional state funding (estimate to be determined).

Total project cost: $3,476,000

Funding sources: Local major bridge program $2,602,160

Local funding: $600,000


Phase
Estimated costs (federal/county/city)
Federal costs
Bridge credit
County costs
City costs*
Total costs
Design (next three tasks)




Environmental (studies, CE document, public involvement)By consultant (estimate fee)--$60,000-$60,000
Geotechnical (borings and recommendations)By consultant (estimate fee)
--$40,000-$40,000
Engineering (field survey, STS, design, r/w plans)By consultant (estimate fee 12% x construction costs)

--$276,720$11,280$288,000

Total design costs--$337,000$11,000$348,000
Right-of-way acquisition (note sidewalk on south side only)Assume temp and perm r/w costs (50% county/50% city)--$6,000$6,000$12,000
ConstructionEstimated (bridge credit for 15%)$1,856,000$348,000$115,000$94,000$2,4000,000
Construction engineering (admin, inspection and materials testing)Estimated (@7% construction)$130,000$24,000$8,000$7,000$168,000
TOTAL PROJECT COSTS
(*estimated year 2023 costs)
City to pay 100% for sidewalk, non-funded enhancements, waterline upgrade, etc
$1,986,000$372,000$466,000$118,000$2,928,000

The City of Twinsburg had been in discussions with Summit County Engineers office for a number of years about replacing the Glenwood Drive bridge over Tinkers Creek. In 2022 the bridge inspection indicated that the structure needed to be posted with load restrictions and was posted with load restriction warning signs. This moved the project up in priority and helped in securing funding for this project. The table below indicates estimated cost in 2023 dollars that will be adjusted for inflation per the funding guidelines based on the actual year of construction. The County is the owner of the bridge and the lead on this project with construction anticipated in 2028.

The City participation in the project is for sidewalks and aesthetics to be included in the design. Also included with the bridge project will be a waterline replacement of a line that is currently attached to the underside of the bridge. The waterline is to be funded 100% funded by the City of Twinsburg and we anticipate submitting an OPWC application in 2026 for additional state funding (estimate to be determined).

Total project cost: $3,476,000

Funding sources: Local major bridge program $2,602,160

Local funding: $600,000


Phase
Estimated costs (federal/county/city)
Federal costs
Bridge credit
County costs
City costs*
Total costs
Design (next three tasks)




Environmental (studies, CE document, public involvement)By consultant (estimate fee)--$60,000-$60,000
Geotechnical (borings and recommendations)By consultant (estimate fee)
--$40,000-$40,000
Engineering (field survey, STS, design, r/w plans)By consultant (estimate fee 12% x construction costs)

--$276,720$11,280$288,000

Total design costs--$337,000$11,000$348,000
Right-of-way acquisition (note sidewalk on south side only)Assume temp and perm r/w costs (50% county/50% city)--$6,000$6,000$12,000
ConstructionEstimated (bridge credit for 15%)$1,856,000$348,000$115,000$94,000$2,4000,000
Construction engineering (admin, inspection and materials testing)Estimated (@7% construction)$130,000$24,000$8,000$7,000$168,000
TOTAL PROJECT COSTS
(*estimated year 2023 costs)
City to pay 100% for sidewalk, non-funded enhancements, waterline upgrade, etc
$1,986,000$372,000$466,000$118,000$2,928,000
Page published: 25 Mar 2026, 02:08 PM